Critical Path Method (CPM): How to Find the Critical Path, With an Example
The critical path method (CPM) finds the longest chain of dependent tasks in a project. That chain sets the shortest possible project duration. Any delay to a task on the critical path delays the whole project. Lean Six Sigma project leaders use CPM to plan implementation and spot which tasks need the closest watch.
What is the critical path in project management?
The critical path is the sequence of tasks with zero float (slack). Float is how long a task can slip without delaying the project end date. Tasks off the critical path have some float. Tasks on it have none.
CPM was developed in the late 1950s by Morgan Walker of DuPont and James Kelley of Remington Rand to plan plant maintenance and construction.
Worked example
| Task | Duration (days) | Depends on |
|---|---|---|
| A. Define requirements | 3 | None |
| B. Train staff | 2 | A |
| C. Configure system | 4 | A |
| D. Pilot and go live | 2 | B and C |
Step 1: forward pass (earliest start and finish)
- A: starts day 0, finishes day 3.
- B: starts day 3, finishes day 5.
- C: starts day 3, finishes day 7.
- D: starts when both B and C finish, so day 7, and finishes day 9.
The project takes 9 days.
Step 2: backward pass (latest start and finish)
- D: must finish by day 9, so latest start is day 7.
- C: latest finish day 7, latest start day 3.
- B: latest finish day 7, latest start day 5.
- A: latest finish day 3 (the earlier of B and C's latest starts), latest start day 0.
Step 3: calculate float
| Task | Earliest start | Latest start | Float |
|---|---|---|---|
| A | 0 | 0 | 0 |
| B | 3 | 5 | 2 |
| C | 3 | 3 | 0 |
| D | 7 | 7 | 0 |
The critical path is A, C, D, with a length of 9 days. Training (B) can slip by up to 2 days without delaying go-live. If system configuration (C) slips by one day, the whole project slips by one day.
How to use the critical path
- Watch critical tasks most closely and report on them first.
- To finish sooner, shorten critical tasks by adding resources (crashing) or running tasks in parallel (fast-tracking).
- Recalculate when tasks change, because the critical path can move.
- Do not assume the riskiest task is on the critical path. Check both.
CPM vs PERT vs Gantt chart
CPM uses one fixed duration per task. PERT uses three estimates (optimistic, most likely and pessimistic) to allow for uncertainty. A Gantt chart is a bar chart that displays the schedule. Most planning software calculates the critical path and shows it on the Gantt chart.
Frequently asked questions
What is the critical path method?
A scheduling method that finds the longest chain of dependent tasks in a project. That chain sets the minimum project duration, and any delay on it delays the project.
How do you find the critical path?
List tasks with durations and dependencies, run a forward pass for earliest start and finish, a backward pass for latest start and finish, then find the tasks with zero float.
What is float in project management?
Float, or slack, is how long a task can be delayed without delaying the project end date. Critical path tasks have zero float.
What is the difference between CPM and PERT?
CPM uses a single duration for each task. PERT uses optimistic, most likely and pessimistic estimates to allow for uncertainty in durations.