Earned Value Management (EVM): Formulas and a Worked Example

Earned value management (EVM) tells you whether a project is ahead or behind schedule and over or under budget, using one consistent set of numbers. It compares what you planned to do, what you actually did and what it cost. This guide explains the three core measures, every common formula, a fully worked example and how earned value management systems are used on large contracts.

The three core measures

MeasureAlso calledMeaning
Planned value (PV)BCWS, budgeted cost of work scheduledThe budget for the work you planned to finish by now
Earned value (EV)BCWP, budgeted cost of work performedThe budget for the work you have actually finished
Actual cost (AC)ACWP, actual cost of work performedWhat you have really spent on the finished work

You also need the budget at completion (BAC), which is the total budget for the whole project.

The key idea is that EV values progress in budget terms. If a task budgeted at $10,000 is half done, it has earned $5,000, whatever it actually cost.

Earned value formulas

Variances

  • Cost variance: CV = EV − AC. Negative means over budget.
  • Schedule variance: SV = EV − PV. Negative means behind schedule.

Performance indices

  • Cost performance index: CPI = EV ÷ AC. Below 1 means you get less than $1 of work for each $1 spent.
  • Schedule performance index: SPI = EV ÷ PV. Below 1 means work is progressing slower than planned.

Forecasts

  • Estimate at completion: EAC = BAC ÷ CPI. This assumes current cost performance continues.
  • Estimate to complete: ETC = EAC − AC. What you still expect to spend.
  • Variance at completion: VAC = BAC − EAC. Negative means a forecast overrun.
  • To-complete performance index: TCPI = (BAC − EV) ÷ (BAC − AC). The cost efficiency you need on the remaining work to finish on budget.

Other EAC formulas exist for different assumptions. If a past overrun was a one-off, use EAC = AC + (BAC − EV). If both cost and schedule problems will continue, use EAC = AC + (BAC − EV) ÷ (CPI × SPI).

Worked example

A team is building a new customer onboarding process. The budget at completion is $100,000 over ten months. At the end of month four:

  • Planned value (PV) = $40,000
  • Earned value (EV) = $35,000
  • Actual cost (AC) = $42,000
MeasureCalculationResultWhat it means
CV35,000 − 42,000−$7,000Over budget by $7,000 so far
SV35,000 − 40,000−$5,000$5,000 of planned work not yet done
CPI35,000 ÷ 42,0000.83About 83 cents of work for each dollar spent
SPI35,000 ÷ 40,0000.875Work is moving at 87.5% of the planned rate
EAC100,000 ÷ 0.8333$120,000Forecast final cost if nothing changes
ETC120,000 − 42,000$78,000Expected spend from here
VAC100,000 − 120,000−$20,000Forecast overrun
TCPI(100,000 − 35,000) ÷ (100,000 − 42,000)1.12The remaining work must run 12% more efficiently than budget to finish on $100,000

The message for the sponsor is clear. The project is behind and over budget, and finishing on budget needs a TCPI of 1.12, much better than the current CPI of 0.83. The team should either find the cause of the overrun and fix it, or reset the budget.

How to set up earned value on a project

  1. Break the work down. Build a work breakdown structure (WBS) down to work packages you can measure.
  2. Schedule and budget each work package. This creates the PV curve over time, called the performance measurement baseline.
  3. Choose how to measure progress. Common rules are 0/100 (credit only when finished), 50/50 (half at start, half at finish) and milestone weighting. Simple rules avoid arguments about percent complete.
  4. Collect actual costs against the same work packages.
  5. Report each period. Plot PV, EV and AC on one chart and review CPI and SPI.
  6. Act on variances. Agree thresholds, such as CPI below 0.95, that trigger a root cause review.

Earned value management systems (EVMS)

On large government and defence contracts, contractors must run a formal earned value management system. The industry standard is EIA-748, which contains 32 guidelines grouped into organisation, planning and budgeting, accounting, analysis and management reports, and revisions and data maintenance. Agencies such as the US Department of Defense and Department of Energy use these 32 guidelines to judge whether a contractor's system is compliant. Smaller projects do not need full EVMS compliance, but the same basic formulas still work.

Limits of earned value

  • It measures cost and schedule, not quality. A project can show a good CPI while building the wrong thing.
  • SPI drifts to 1 at the end. When all work is done, EV equals PV whatever the delay. Use the critical path to judge real schedule risk late in a project.
  • It depends on honest progress data. Inflated percent complete makes every number wrong.

Earned value and process improvement

EVM tells you that a project is drifting. It does not tell you why. That is where Lean Six Sigma helps. When CPI falls, a Pareto chart of cost overruns by work package shows where the money goes. A fishbone diagram helps the team test causes such as rework, unclear requirements or waiting for approvals. Plotting CPI each month on a control chart shows whether a dip is a real change or normal variation. Pair EVM with the critical path method for schedule risk, and you have a strong project control system.

Frequently asked questions

What is earned value management?

Earned value management is a project control method that compares planned value, earned value and actual cost to measure schedule and cost performance and forecast the final cost.

What is the formula for earned value?

Earned value equals the budget for the work actually completed. For example, if a task budgeted at $10,000 is 50% complete, its earned value is $5,000.

How do you calculate CPI and SPI?

CPI equals earned value divided by actual cost. SPI equals earned value divided by planned value. A value below 1 means the project is over budget or behind schedule.

What is the EAC formula?

The most common formula is EAC = BAC ÷ CPI, which assumes current cost performance continues. Other versions apply when an overrun is a one-off or when schedule problems also affect cost.

What is TCPI?

The to-complete performance index is (BAC − EV) ÷ (BAC − AC). It shows how efficiently the remaining work must be done to finish on budget.

What is ANSI/EIA-748?

EIA-748 is the industry standard for earned value management systems. It sets out 32 guidelines that large contractors must meet on many government projects.