Risk Assessment Matrix
Risk Assessment Matrix
Prioritise project threats by likelihood and severity.
Risk Assessment Matrix
Browser-only calculations · No input data saved
Worked example results
| Risk | Risk score / 25 |
|---|---|
| Data unavailable | 12 |
| Sponsor change | 10 |
Rounded for display only. Export includes the inputs, results, method and assumptions. Refreshing or leaving the tool clears entered data.
Original advanced tool & legacy export options
The original migrated on-site tool is retained below so existing features, industry samples and legacy exports remain available. It is a local page, not another Base44 app. Its older scoring conventions may differ from the transparent native helper above.
How to use Risk Assessment Matrix
- Load the worked example to see the required input format.
- Prioritise project threats by likelihood and severity. Use consistent units, periods and definitions.
- Select Calculate, review the assumptions and export the result for your project evidence.
Formula and method
Risk score = likelihood × severity, each on an agreed 1–5 scale.
Interpretation and assumptions
Risk matrices are ordinal prioritisation aids. Include controls, owners and due dates in the risk register; do not equate these scores with probabilities or financial loss.
Results support professional judgement. They are not a certification of process stability, a financial commitment or a substitute for study design.
What is a risk assessment matrix?
A risk assessment matrix ranks risks by two ratings: how likely the risk is to happen and how severe the impact would be. Multiplying the two gives a score that helps you decide which risks need action first. In a Lean Six Sigma project, the team uses it in the Define phase to assess project risks, and again in the Improve phase to assess the risks of a new solution.
How to calculate risk assessment scores
Risk score = likelihood × severity, each rated from 1 to 5. Scores run from 1 to 25.
| Rating | Likelihood | Severity |
|---|---|---|
| 1 | Rare | Negligible |
| 2 | Unlikely | Minor |
| 3 | Possible | Moderate |
| 4 | Likely | Major |
| 5 | Almost certain | Severe |
Agree what each rating means before you score. For example, "Major" might mean a delay of more than one month or a cost over $50,000. Without shared definitions, two people will score the same risk differently.
Worked example
| Risk | Likelihood | Severity | Score |
|---|---|---|---|
| Baseline data is unavailable | 3 | 4 | 12 |
| Sponsor changes role | 2 | 5 | 10 |
| Key analyst on leave during Measure | 4 | 2 | 8 |
The data risk ranks first. The team responds by confirming data access in week one. The sponsor risk scores lower, but its severity of 5 means it still needs a named owner and a plan, such as a backup sponsor agreed with the steering group.
Reading the results
Many organisations band scores, for example 1 to 4 low, 5 to 9 medium, 10 to 16 high and 20 to 25 extreme. Use your organisation's own bands if it has them. Always review high-severity risks on their own, because a rare but severe risk can score the same as a frequent nuisance.
A matrix score is a ranking aid, not a probability or a dollar figure. Record each risk in a register with an owner, a response and a review date. For process failure risks, use FMEA, which adds a detection rating. The Green Belt course covers both.
Keep the evidence connected
Green Belt course · Black Belt course · Process capability definition · Sigma level definition
Frequently asked questions
How do you calculate a risk assessment score?
Rate likelihood and severity on an agreed scale, usually 1 to 5, then multiply them. A risk rated 3 for likelihood and 4 for severity scores 12 out of 25.
What is a 5x5 risk matrix?
A 5x5 risk matrix has five likelihood ratings and five severity ratings. Each risk lands in one of 25 cells, and the product of the two ratings ranks the risks from 1 to 25.
What score is a high risk?
It depends on your organisation's bands. A common approach treats 10 to 16 as high and 20 to 25 as extreme. Review any risk with a severity of 5 regardless of its total score.
What is the difference between a risk matrix and FMEA?
A risk matrix uses likelihood and severity. FMEA adds a third rating for how well current controls detect the failure, and multiplies all three into a risk priority number. FMEA suits detailed process risks.
How do I use the risk assessment matrix?
Prioritise project threats by likelihood and severity. Load the example first, then replace all inputs with consistent process data and select Calculate. Risk score = likelihood × severity, each on an agreed 1–5 scale.
What assumptions matter for risk assessment matrix?
Risk matrices are ordinal prioritisation aids. Include controls, owners and due dates in the risk register; do not equate these scores with probabilities or financial loss.
Are my calculator inputs saved or sent to a server?
These native calculations run in this browser tab. Inputs are not sent to a server or saved by this calculator. Download the result if you need a record; leaving or refreshing clears the form.